Type |
Description (PDF) |
Announcement No. |
Issuance Date |
Due Time & Date |
IFB |
Ugum Reservoir No. 2 Construction |
IFB-06-ENG-2023 |
01/18/23 |
10:00 AM, 03/03/23 |
RFP |
Construction Management Services for Ugum No. 2 Reservoir |
RFP-04-ENG-2023 |
01/10/23 |
10:00 AM, 02/14/23 |
IFB |
Variable Frequency Drive System, for Ga’an Sewer Pump Station
• Bid Amendment No. 1 New Bid Opening Date and Time: January 17, 2023, 2:00 PM
• Bid Amendment No. 2 New Bid Opening Date and Time: January 31, 2023, 2:00 PM
• Response to Inquiry No. 1
• Bid Amendment No. 3 New Bid Opening Date and Time: January 31, 2023, 2:00 PM
• Bid Amendment No. 4 New Bid Opening Date and Time: February 07, 2023, 2:00 PM
| IFB 2023-09 |
12/28/22 |
10:00 AM, 01/17/23 |
IFB |
Mini Backhoe with Trailer
• Bid Amendment No. 1 New Bid Opening Date and Time: January 10, 2023, 2:00 PM
• Bid Amendment No. 1 New Bid Opening Date and Time: January 18, 2023, 2:00 PM |
IFB 2023-08 |
12/16/22 |
10:00 AM, 01/10/23 |
IFB |
Boom Truck Crane
• Bid Amendment No. 1 New Bid Opening Date and Time: January 09, 2023, 2:00 PM
• Bid Amendment No. 2 New Bid Opening Date and Time: January 24, 2023, 2:00 PM
• Bid Amendment No. 3 New Bid Opening Date and Time: February 08, 2023, 2:00 PM
• Response to Inquiry No. 1 |
IFB 2023-02 |
12/16/22 |
10:00 AM, 01/09/23 |
IFB |
Ugum Water Treatment Plant Rehabilitation
• Addendum No. 1
• RFI Response No. 1 to Contractor Inquiries
• Addendum No. 2
• RFI Response No. 2 to Contractor Inquiries
• RFI Response No. 3 to Contractor Inquiries
| IFB-05-ENG-2023 |
12/02/22 |
10:00 AM, 01/06/23 |
IFB |
Central Guam Reservoirs – Manenggon Reservoir No. 2 and Tamuning Reservoir No. 2
• Addendum No. 1
• Addendum No. 2
• RFI Response No. 1 to Contractor Inquiries
| IFB-01-ENG-2023 |
12/02/22 |
3:00 PM, 12/28/22 |
Sole Source |
Prepaid, First class, Pre-sorted Postage for Permits |
US Postal Services, Contract Term: One (1) Year |
11/23/22 |
IFB |
Groundwater Wells A-02, A-07, A-12, D-05, and F-03 Rehabilitation (Re-Bid)
• RFI Response No. 1 to Contractor Inquiries
• Addendum No. 1
• RFI Response No. 2 to Contractor Inquiries
• Addendum No. 2
• Addendum No. 3
• RFI Response No. 3 to Contractor Inquiries
| IFB-02-ENG-2023 |
11/17/22 |
3:00 PM, 12/14/22 |
RFP |
Design and CM Services for Waterline Replacement of Various Bridges
• RFI Response No. 1 to Contractor Inquiries
| RFP-03-ENG-2023 |
11/17/22 |
10:00 AM, 12/09/22 |
RFP |
Indefinite Delivery/Indefinite Quantity (ID/IQ) for Water and Wastewater Hydraulic Modeling Services |
RFP-02-ENG-2023 |
11/15/22 |
10:00 AM, 12/06/22 |
IFB |
Fire Hydrant “Wet Barrel”
• Bid Amendment No. 1 New Bid Opening Date and Time: December 13, 2022 10:00 AM |
IFB 2023-03 |
11/09/22 |
10:00 AM, 11/29/22 |
RFP |
Construction Management Services for Tamuning and Manenggon Reservoirs
• RFI Response No. 1 to Contractor Inquiries
• Addendum No. 1
| RFP-01-ENG-2023 |
10/28/22 |
10:00 AM, 11/18/22 |
IFB |
(Re-Bid) Storage Space Lease |
IFB 2023-07 |
10/24/22 |
10:00 AM, 11/23/22 |
RFP |
Collection Services
• Amendment No. 1 New-Submittal date and time scheduled for November 03, 2022 @ 3:00 p.m.
• Amendment No. 2 New-Submittal date and time scheduled for November 21, 2022 @ 3:00 p.m.
• Amendment No. 3 New-Submittal date and time scheduled for December 05, 2022 @ 3:00 p.m.
• Amendment No. 4 New-Submittal date and time scheduled for December 19, 2022 @ 3:00 p.m.
• Amendment No. 5 New-Submittal date and time scheduled for January 04, 2023 @ 3:00 p.m.
• Amendment No. 6 New-Submittal date and time scheduled for January 25, 2023 @ 3:00 p.m.
• Amendment No. 7 New-Submittal date and time scheduled for February 15,2023 @ 3:00 p.m.
| RFP 2022-02 |
09/26/22 |
3:00 PM, 10/18/22 |
RFP |
Indefinite Delivery/Indefinite Quantity (ID/IQ) Professional Project/Construction Management for Islandwide Sewer Collection/Transmission System Repair, Rehabilitation, and Replacement
• Response to RFI No. 1
• Addendum No. 1
| RFP-06-ENG-2022 |
09/16/22 |
10:00 AM, 10/07/22 |
RFP |
Indefinite Delivery/Indefinite Quantity (ID/IQ) for Engineering Design and Construction Management Services for the Implementation of District Metered Areas |
RFP-07-ENG-2022 |
08/30/22 |
10:00 AM, 09/20/22 |
IFB |
Storage Space Lease
• Notification to Bidders
| IFB 2022-17 |
08/09/22 |
10:00 AM, 09/27/22 |
IFB |
Printer Pool Plan
• Bid Amendment No. 1 New Bid Opening Date and Time: August 30, 2022 10:00 AM
• Bid Amendment No. 2 New Bid Opening Date and Time: September 13, 2022 10:00 AM
• Bid Amendment No. 3 New Bid Opening Date and Time: September 28, 2022 10:00 AM
• Bid Amendment No. 4 New Bid Opening Date and Time: October 11, 2022 10:00 AM
• Response to Inquiry No. 1
• Bid Amendment No. 5 New Bid Opening Date and Time: October 25, 2022 10:00 AM
• Response to Inquiry No. 2
• Bid Amendment No. 6 New Bid Opening Date and Time: November 03, 2022 10:00 AM
• Response to Inquiry No. 3
| IFB 2022-19 |
08/04/22 |
10:00 AM, 08/23/22 |
IFB |
Defective Submersible Pumps & Motors and other Scrap Metals
• Response to Inquiry No. 1
| IFB 2022-08 |
07/05/22 |
10:00 AM, 07/26/22 |
IFB |
Global Positioning System (GPS) Equipment
• Bid Amendment No. 1 New Bid Opening Date and Time: July 26, 2022 2:00 PM
• Bid Amendment No. 2 New Bid Opening Date and Time: August 02, 2022 2:00 PM
• Notice of Cancellation
| IFB 2022-11 |
06/23/22 |
2:00 PM, 07/12/22 |
IFB |
Sewer Cleaner Truck with Hydro Excavation System
• Bid Amendment No. 1 New Bid Opening Date and Time: July 27, 2022 10:00 AM
• Bid Amendment No. 2 New Bid Opening Date and Time: August 04, 2022 10:00 AM
• Bid Amendment No. 3 New Bid Opening Date and Time: August 11, 2022 10:00 AM
• Response to Inquiry No. 1
| IFB 2022-10 |
06/23/22 |
10:00 AM, 07/12/22 |
IFB |
VX Rail Pro Support
• Bid Amendment No. 1 New Bid Opening Date and Time: July 14, 2022 10:00 AM
• Response to Inquiry No. 1
| IFB 2022-07 |
06/17/22 |
10:00 AM, 07/05/22 |
IFB |
Aplacho Sewer Pump Station Drainage and Roadway Improvements
• Response to RFI Nos. 1 and 2
• Addendum No. 1
• Bid Form
• Aplacho Sewer PS Drawings
| IFB-02-ENG-2022 |
06/16/22 |
10:00 AM, 08/16/22 |
RFP |
Independent Financial Audit Services |
RFP-2022-03 |
06/09/2022 |
3:00 PM, 07/14/22 |
RFP |
Adacao Water and Sewer Infrastructure Design Services |
RFP-09-ENG-2022 |
05/27/2022 |
10:00 AM, 06/30/22 |
RFI |
Network Service Capabilities
• Amendment No. 1 New Submission Date and Time: May 25, 2022 5:00 PM
• Response to Inquiry No. 1 |
RFI 2022-001 |
05/04/22 |
5:00 PM, 05/18/22 |
IFB |
Galvanized Pipes
• Response to Inquiry No. 1
• Bid Amendment No. 1 New Bid Opening Date and Time: June 15, 2022 10:00 AM
• Bid Amendment No. 2 New Bid Opening Date and Time: June 29, 2022 10:00 AM
• Response to Inquiry No. 2
• Bid Amendment No. 3 New Bid Opening Date and Time: July 06, 2022 10:00 AM |
IFB 2022-05 |
05/04/22 |
10:00 AM, 05/25/22 |
RFP |
Construction Management Services for Brigade II Booster Pump Station |
RFP-02-ENG-2022 |
04/28/22 |
5:00 PM, 05/23/22 |
RFP |
Indefinite Delivery/Indefinite Quantity (ID/IQ) for Engineering Design and CM Services for Undersized Waterline Replacement |
RFP-01-ENG-2022 |
04/27/22 |
5:00 PM, 05/20/22 |
RFP |
Construction Management Services for Pressure Zone Realignment Construction Phase II |
RFP-05-ENG-2022 |
04/26/22 |
5:00 PM, 05/19/22 |
RFP |
Indefinite Delivery/Indefinite Quantity (ID/IQ) for Engineering Design and CM Services for ACP Waterline Replacement
• Addendum No. 1 |
RFP-04-ENG-2022 |
04/22/22 |
5:00 PM, 05/17/22 |
RFP |
Indefinite Delivery/Indefinite Quantity (ID/IQ) for Engineering Design and CM Services for Waterline Replacement and Upgrades
• RFI Response No. 1 to Contractor Inquiries
• Addendum No. 1 |
RFP-03-ENG-2022 |
04/19/22 |
5:00 PM, 05/13/22 |
IFB |
Upper Tumon Office Security Services
• Bid Amendment No. 1 New Bid Opening Date and Time: April 07 , 2022 10:00 AM
• Bid Amendment No. 2 New Bid Opening Date and Time: April 14, 2022 10:00 AM
• Response to Inquiry No. 1
• Bid Addendum No. 1 |
IFB 2022-12 |
03/24/22 |
10:00 AM, 03/31/22 |
IFB |
Property Insurance, General Liability Insurance, Directors and Officers Liability Insurance, Automobile Insurance, Crime and Cyber Liability Insurance
• Non Disclosure Agreement
• Response to Inquiry No. 1 Site Visit
• Bid Amendment No. 1
• Response to Inquiry No. 2 Partial Response
• Response to Inquiry No. 3 Partial Response
• Response to Inquiry No. 4
• Photo Pipe Info
• Bid Amendment No. 2 New Bid Opening Date and Time: April. 21, 2022 10:00 AM |
IFB 2022-09 |
03/03/22 |
10:00 AM, 04/14/22 |
IFB |
Fire Hydrant Wet Barrel
• Bid Amendment No. 1 New Bid Opening Date and Time: April. 05, 2022 10:00 AM
• Response to Inquiry No. 1
• Response to Inquiry No. 2
• Bid Amendment No. 2 New Bid Opening Date and Time: April. 19 , 2022 10:00 AM
• Response to Inquiry No. 3 |
IFB 2022-03 |
03/03/22 |
10:00 AM, 03/22/22 |
RFP |
Specialized Sewer Cleaning Evaluation and Training
• Amendment No. 1 New-Submittal date and time scheduled for March 08, 2022 @ 3:00 p.m.
• Amendment No. 2 New-Submittal date and time scheduled for March 15, 2022 @ 3:00 p.m.
• Response to Inquiry No. 1 |
RFP 2022-01 |
02/09/22 |
3:00 PM, 02/28/22 |
IFB |
Diesel Fuel Oil No. 2 and Automotive Gasoline, Regular Unleaded
• Bid Amendment No. 1 New Bid Opening Date and Time: Dec. 30, 2021 10:00 AM
• Bid Amendment No. 2 New Bid Opening Date and Time: Jan. 11, 2022 10:00 AM
• Bid Amendment No. 3 New Bid Opening Date and Time: Jan. 31, 2022 10:00 AM
• Response to Inquiry No. 1
• Response to Inquiry No. 2 |
IFB 2022-01 |
11/24/21 |
10:00 AM, 12/15/21 |
IFB |
Control Panel
• Bid Amendment No. 1 New Bid Opening Date and Time: Dec. 14, 2021 10:00 AM
• Response to Inquiry No. 1
• Bid Amendment No. 2 New Bid Opening Date and Time: Dec. 21, 2021 10:00 AM
• Response to Inquiry No. 2 |
IFB 2022-04 |
11/16/21 |
10:00 AM, 11/24/21 |
IFB |
Ugum Chemicals
• Bid Amendment No. 1 New Bid Opening Date and Time: September 07, 2021 10:00 AM
• Response to Inquiry No. 1
• Response to Inquiry No. 2 |
IFB 2021-16 |
08/05/21 |
10:00 AM, 08/24/21 |
IFB |
Various Size Automated Meter Reading (AMR) Water Meters
• Bid Amendment No. 1 New Bid Opening Date and Time: September 08, 2021 10:00 AM
• Response to Inquiry No. 1
• Addendum No. 1
• Bid Amendment No. 2 New Bid Opening Date and Time: Sept 14, 2021 10:00 AM
• Bid Amendment No. 3 New Bid Opening Date and Time: Sept 24, 2021 10:00 AM
• Bid Amendment No. 4 New Bid Opening Date and Time: Oct 5, 2021 10:00 AM
• Bid Amendment No. 5 New Bid Opening Date and Time: Oct 15, 2021 10:00 AM
• Bid Amendment No. 6 New Bid Opening Date and Time: Oct 27 2021 10:00 AM
• Bid Amendment No. 7 New Bid Opening Date and Time: Nov 10 2021 10:00 AM
• Bid Amendment No. 8 New Bid Opening Date and Time: Dec 09 2021 10:00 AM
• Bid Amendment No. 9 New Bid Opening Date and Time: Dec 23 2021 10:00 AM
• Bid Amendment No. 10 New Bid Opening Date and Time: Jan 13 2022 10:00 AM
• Bid Amendment No. 11 New Bid Opening Date and Time: Feb 10 2022 10:00 AM
• Bid Amendment No. 12 New Bid Opening Date and Time: March 10 2022 10:00 AM
• Bid Amendment No. 13 New Bid Opening Date and Time: March 24 2022 10:00 AM
• Bid Amendment No. 14 New Bid Opening Date and Time: April 07 2022 10:00 AM
• Bid Amendment No. 15 New Bid Opening Date and Time: April 21 2022 10:00 AM
• Bid Amendment No. 16 New Bid Opening Date and Time: May 05, 2022 10:00 AM
• Bid Amendment No. 17 New Bid Opening Date and Time: May 19, 2022 10:00 AM
• Notice of Cancellation |
IFB 2021-17 |
07/22/21 |
10:00 AM, 08/11/21 |
RFP |
Risk Management and Insurance Consulting Services
• Amendment No. 1 New-Submittal date and time scheduled for July 30, 2021 @ 4:00 p.m.
• Amendment No. 2 New-Submittal date and time scheduled for August 06, 2021 @ 4:00 p.m.
• Amendment No. 3 New-Submittal date and time scheduled for August 13, 2021 @ 4:00 p.m.
• Amendment No. 4 New-Submittal date and time scheduled for August 16, 2021 @ 4:00 p.m.
• Amendment No. 5 New-Submittal date and time scheduled for August 27, 2021 @ 4:00 p.m.
• Response to Inquiry No. 1 |
RFP 2021-04 |
06/18/21 |
4:00 PM, 07/20/21 |
IFB |
NOTIFICATION: Route 1-Asan-Adelup, Hagatna Sewerline Rehabilitation and Replacement – Phase 2 |
|
|
|
IFB |
NOTIFICATION: Northern Guam Lens Aquifer (NGLA) Monitoring System Expansion and NGLA Monitoring System Rehabilitation |
|
|
|
IFB |
NOTIFICATION: Upgrade of the Northern District Wastewater Treatment Plant (Clearing and Grading) |
|
|
|